Work began this week on Woodward’s west side on the second leg of the Let’s Connect trail linking the Raccoon River Valley Trail to the High Trestle Trail.

The first phase of the $5 million connector-trail project, completed in October 2018, comprised 1.5 miles of trail starting in Perry and working eastward to 130th Street. Phase two begins at the city limits of Woodward at S Avenue and moves westward one mile to R Avenue.

Phase three will continue building westward to Quinlan Avenue. Scheduling of the third and fourth construction phases will depend on federal and state recreational trail grant cycles and the pace of private and corporate donations.